Project Progress Report Milestone 2, Phase 1)

Overview

Multipurpose Hall cum Guest House construction

Work in progress for constructing Multipurpose Hall at project site of Dr Babasaheb Ambedkar International Education Center.

Donations received for this work (Amount required 30L INR)
Target 30L
Expenditures done
Budget = 30L 10%
Total Construction Work Progress
8%

Here is the detailed project progress, for the first Phase. A multi-purpose Hall cum Guest house.

The intended use of this facility, is not just limited to the following

  1. Study Hall for local students
  2. A small library
  3. facility for coaching classes
  4. Hall for Meditation
  5. A guest house for visitors from Japan
  6. And many more…

Detail Happenings

Land Breaking : 19 April 2023

Internal Meetings concluded that one contractor is Finalised among the three proposals. He has already worked on the site for Guard House construction. Detailed Quotations etc. discussed and finalised to be around 30L.

Leave a Comment

Your email address will not be published. Required fields are marked *